欧美性爽xxxzzzzzzzz,午夜AV福利老牛,久久99色,国产碰碰福利

網(wǎng)站公告-NOTICE
航豐實業(yè)·產(chǎn)品分類
聯(lián)系我們
濟(jì)南航豐實業(yè)有限公司

電話:15168870138
聯(lián)系人:龐經(jīng)理

網(wǎng)址:http://  

廠址: 德州市禹城市莒鎮(zhèn)產(chǎn)業(yè)園26棟

經(jīng)銷商地址:天橋區(qū)建華五金市場東區(qū)5-1  

魯ICP備09095923號-1

新聞資訊

當(dāng)前位置:首頁 / 新聞資訊

電纜橋架穿墻安裝時選用的密封性設(shè)備

橋架與各種各樣管道交叉時,其凈間隔應(yīng)達(dá)到以下規(guī)定:
When the bridge crosses various pipelines, the net spacing shall meet the following requirements:
(1)橋架與--般制作工藝管道交叉時,不小于300毫米。
(1) When the bridge crosses the general manufacturing process pipe, it shall not be less than 300mm.
(2)橋架與有腐蝕性液體管道下方或有腐蝕性氣體管道上方交叉時,應(yīng)不小于500毫米,且在交接處用防腐蝕蓋板將橋架維護(hù)起來,其蓋板長度應(yīng)不小于d+2000毫米,(d為管道外徑)。
(2) When the bridge crosses below the corrosive liquid pipeline or above the corrosive gas pipeline, it shall not be less than 500 mm, and the bridge shall be maintained with an anti-corrosion cover plate at the junction. The length of the cover plate shall not be less than d+2000 mm, (D is the outer diameter of the pipeline).
(3)橋架與供熱管道交叉,供熱管道有隔熱材料時,應(yīng)不小于500毫米無隔熱材料時,應(yīng)不小于1000毫米,且在交接處應(yīng)用隔熱材料(比如石棉板)將橋架維護(hù)起來,隔熱材料長度應(yīng)不小于d+2000毫米(d為供熱管道隔熱材料的外徑)。
(3) The bridge crosses the heat supply pipeline. When the heat supply pipeline has heat insulation materials, it should not be less than 500mm. When there is no heat insulation materials, it should not be less than 1000mm. And at the junction, heat insulation materials (such as asbestos board) should be used to maintain the bridge. The length of the heat insulation materials should not be less than d+2000 mm (D is the outer diameter of the heat insulation materials of the heat supply pipeline).
橋架穿墻安裝時,應(yīng)依據(jù)自然環(huán)境條件,選用密封性設(shè)備:
When the bridge is installed through the wall, the sealing equipment shall be selected according to the natural environmental conditions:
(1)橋架從正常情況下自然環(huán)境穿墻進(jìn)到防火、防爆型的自然環(huán)境時,墻上應(yīng)安裝對應(yīng)的密封性設(shè)備。
(1) When the bridge passes through the wall from the natural environment under normal circumstances to the fire-proof, safe and explosion-proof natural environment, the corresponding sealing equipment shall be installed on the wall.
(2)橋架從房間內(nèi)穿墻戶外時,在墻的外側(cè)應(yīng)采用防水防雨具體措施。
(2) When the bridge passes through the wall from the room to the outdoors, specific waterproof measures shall be taken outside the wall.
(3)橋架從房間內(nèi)穿墻戶外較高空安裝時,橋架先要向下傾斜增加適量間隔,隨后再向上搭建,防止雨水順橋架流入房間內(nèi)。
(3) When the bridge is installed from the wall in the room to a higher height outdoors, the bridge should first be tilted downward to increase an appropriate interval, and then built upward to prevent rainwater from flowing into the room along the bridge.
(4)橋架過伸縮沉降縫時,電纜線橋應(yīng)斷開連接,斷開連接間隔以100毫米上下為宜。
(4) When the cable tray passes through the expansion settlement joint, the cable bridge should be disconnected, and the disconnection interval should be 100 mm up and down.
兩組電纜線橋在同一個橫梁上安裝時,兩兩之間的凈間隔應(yīng)不小于50毫米。
When two sets of cable bridges are installed on the same beam, the net spacing between the two should not be less than 50mm.
鋪設(shè)10kV及之上電纜線的橋架多層安裝時,其層間隔一般不小于300毫米。
When the cable tray laying 10kV and above is installed in multiple layers, the layer spacing is generally not less than 300mm.
以上就是為大家介紹的有關(guān)濟(jì)南電纜橋架的詳細(xì)的介紹,希望對您有所幫助.如果您有什么疑問的話,歡迎聯(lián)系我們.我們將以的態(tài)度,為您提供服務(wù)http://
The above is a detailed introduction about Jinan cable tray, which I hope will be helpful to you If you have any questions, please contact us We will provide you with professional service http://
 
qq
售前咨詢熱線
15168870138
售后咨詢熱線
13465410318